Completed Projects:
Electro-Coat Paint Tank Reline Project
Electro-Coat Paint Tank Reline Project

Project Description. The old lining material and E Coat material was removed from main dip tank, weir tank and pump wells by high pressure water jetting with 36,000 PSI to clean the steel surfaces to bare metal. All steel surfaces were abrasive blasted to meet SSPC-SP5 (White Metal) with a three mil minimum anchor profile.
All prepared surfaces received lining system based on primer and silica filled, glass reinforced, epoxy lining, applied to a nominal thickness of 3/16" in accordance with the manufacturer's recommendations and instructions.
Work Performed:
Removal chemically attacked and disbanded Lining Hydro blast with 36,000 psi
Surface preparation- SSPC-SP-5 (NACE1) - white metal abrasive blast
Lining: 150 mils woven cloth reinforced Epoxy Lining
Inspection for film discontinuity: High Voltage Sparktest- 15,000 Volts
Installation of FRP Components: Coves, Anode Supports, Crash Rails, Stairs and Pipe inserts

Our Work. Our Results. Your Confidence.
At Ultimate Corrosion Control, we measure our success by the results we deliver. From power plants and chemical facilities to water treatment systems and industrial infrastructure, our completed projects showcase the proven performance of our coatings and corrosion control solutions.
Contact us at 248-388-3525 for more information or to request a detailed project quotation.
Completed Projects Index
- Waste Water Treatment - FGD System
- Tiger Creek Generation Facility
- Mesquite Power Generation Facility
- Trimble County Generation Facility
- Electro-Coat Paint Tank Reline
- E-Coat Secondary Containment